SCADA & HMI
Combined Cycle Power Plant Commissioning – Hail
i4Serv supported the commissioning of a combined cycle power plant for the National Electricity Generation Company in Hail, covering redundant S7-400 PLCs, ICONICS SCADA and Modbus TCP integration.
Overview
i4Serv contributed to the commissioning phase of a combined cycle power plant for the National Electricity Generation Company in Hail, Saudi Arabia. The scope covered modification and closure of critical punch list items, communication between redundant Siemens S7-400 PLC systems, SCADA upgrades on the ICONICS platform, Modbus TCP communication between integrated systems, and OPC configuration and troubleshooting.
What we delivered
- Modification and closure of critical punch list items
- Communication between redundant Siemens S7-400 PLC systems
- SCADA upgrades on the ICONICS platform
- Modbus TCP communication between integrated systems
- OPC configuration and troubleshooting
Impact
Reliable system integration and operational stability achieved in a high-demand energy environment, with complex commissioning-phase issues resolved.